Heritage Road Layover – Tree Removals

Brampton, Ontario

As part of Metrolinx’s early works for future transit expansion, MCBC Milestone Environmental Remediation LP (MCBCMER) removed 30 trees within the designated construction zone at the proposed Heritage Road Layover site. The project focused on vegetation clearing in the rail corridor to prepare the site for upcoming development.

Project Scope

Cleared and removed designated trees in accordance with Metrolinx’s Vegetation Guideline and local bylaws.

Key Services

Vegetation clearing
Environmental compliance
Site preparation

Key Challenges

Strict adherence to local environmental and safety guidelines
Maintaining project schedule while working in an active rail corridor

Project Solutions

Coordinated closely with Metrolinx and local authorities to ensure compliance
Completed all work safely, on time, and in full alignment with regulatory standards